ATM FACILITIES MANAGEMENT TAPE, FLOOR DOTS,
& SPECIALTY SYMBOL APPLICATION INSTRUCTIONS
|
|
|
|
| |
Air and
surface temperature must be 50°F (10°C). |
| |
Surface must be
completely dry. |
| |
Surface
must be clean and free of any contaminants which may include but not limited to oils,
grease, sand, dirt, dust, loose aggregate, curing compound, mud, soil and salt. |
 |
| |
If
concrete is less than 45 days old, or has never been opened to traffic, the curing
compound must be completely removed by pressure washing, sandblasting, or grinding the
surface. |
 |
| |
Do not apply product
directly on seams, joints, deteriorating markings or substrates. |
| |
Tapes
applied directly over seams and joints must be cut through 1" on both sides of the
joints or seams to prevent de-bonding of the tape. |
 |
| |
ALWAYS USE BUTT
SPLICES. |
| |
Firmly
tamp the product in the same direction as it was applied on the initial pass. A minimum of
three passes total. Use a tamper device with a minimum 200 lb. (90kg) load and a tamping
surface a minimum 2" wider than the width of tape being applied. Never twist the
tampering device during tamping. Repeat tamping as necessary to insure tape has completely
confirmed to the surface. |
 |
 |
 |
 |
 |
| |
All users
should test a small piece of product for satisfactory adhesion prior to installing large
portions. |
 |
|
|
|
|
|
|
|